How Long Does a Kitchen Remodel Take? (Lewisville, TX)

Free Estimate on SiteCalls Answered by a Live Person, 24/7Background-Checked TechniciansA Local Team in Lewisville
New painted shaker cabinets with an organized deep drawer
A remodeled kitchen with a waterfall island and wood cabinets
An open kitchen and dining area after a remodel
A remodeled hall bathroom with patterned floor tile and painted walls
A wood double vanity with two mirrors after a bathroom remodel
A finished backyard cottage with a small covered porch
A new roof with clean valleys and new flashing
A new multi-panel patio door opening a kitchen to the patio
Every visit starts with

Free written scope consultation - allowances, timeline, and change-order rules on paper before a single trade is scheduled

We have financing partners for your dream remodel*On approved credit; ask us about your options
Get your free estimate
Explore

Styles & brands we work with

  • Kitchen remodeling
  • Bathroom remodeling
  • Home additions & ADU
  • Roofing
  • Windows & doors
  • Driveway & pavers
  • Fence
Before & after

See the difference

Before - Recent ProjectBeforeAfter - Recent ProjectAfter
Recent Project
Before - Full RestorationBeforeAfter - Full RestorationAfter
Full Restoration
Before - Complete UpgradeBeforeAfter - Complete UpgradeAfter
Complete Upgrade

How Long Does a Kitchen Remodel Take in Lewisville, TX? The Honest Timeline

A full kitchen remodel in Lewisville typically takes 10 to 16 weeks once you account for City of Lewisville permit inspection windows and premium material lead times. The 6-to-12-week number you see online is only accurate if you’ve already factored in a KraftMaid cabinet order and a Cambria quartz template-to-install wait. If nobody built those into your calendar, you’re counting days on a schedule that doesn’t match how construction actually works here. Here’s the timeline we actually work to.

Groundwork Construction Co. of Lewisville builds that schedule around real constraints, not best-case ones. Our technicians have up to 12 years of experience, and every project is covered by the 730-Day Done Right Promise. When you’re ready to talk specifics, call (844) 560-4467 and a live person picks up, any hour.

Installers leveling a new base cabinet during a kitchen remodel

Phase-by-Phase: Where the Days Actually Go

Most of the anxiety around kitchen timelines comes from a calendar that skips the boring parts. Here’s each phase with honest day counts, from design through final walkthrough.

Phase Typical Duration
Design & permit submittal 1-3 weeks
City of Lewisville permit approval 5-10 business days
Demolition 1-3 days
Rough-in (electrical, plumbing, HVAC) 3-7 days
Inspection hold point 1-5 days
Cabinet installation 2-5 days
Countertop template-to-install 10-14 days
Finish work 3-5 days

Add those up on the high side and you land near the 14-week mark. That’s not padding. That’s what the sequence genuinely requires when you don’t cut corners. For context on what each phase costs in this market, full kitchen remodels in Lewisville run $14,000-$45,000, with smaller kitchens at $9,000-$20,000. Cabinets alone land at $4,000-$13,000, countertops at $2,000-$6,500.

For the phased approach we follow from tear-out to close-up, our Kitchen Remodeling service page walks through scope and materials. This page is about the clock.

The Inspection Hold Point Nobody Warns You About

Here’s where generic timelines break down. Before walls close, a City of Lewisville inspector has to sign off on your rough-in electrical, plumbing, and mechanical work. That inspection sits between two phases and adds 1-5 days to the calendar while you wait for the appointment window.

Contractors who quote you an aggressive six-week turnaround are either skipping the hold or hoping it goes fast. Both are mistakes. Rushing past an inspection, or having the walls buttoned up before the sign-off lands, creates code violations that cost more time to fix than the wait itself. When we have to open a wall back up because the inspection wasn’t scheduled properly, that’s a week gone.

Lewisville’s older housing stock makes this worse. Much of the core is 1960s-1980s brick ranch and pier-and-beam construction, and kitchens from that era often have wiring and plumbing that don’t meet current code. If we find aluminum branch wiring or galvanized supply lines during demo, the rough-in scope grows, and so does the inspection phase. It’s better to plan for that than to discover it in week five. Our team has done enough of these in Lewisville to know the older homes near Old Town tend to need a closer look at rough-in before we price the job.

One more local wrinkle: North Texas black gumbo clay moves constantly with the wet-dry cycle, and older slab-on-grade kitchens sometimes show cracked tile or shifting thresholds before demo even starts. If floor movement shows up during tear-out, it has to be addressed before cabinets go in, or the new install inherits the same problem. We build in a small buffer for that.

A new front yard fence with a matching gate

Why Cabinet and Countertop Lead Times Are Part of the Schedule

Custom cabinet orders like KraftMaid run 4-8 weeks from order to delivery. That lead time doesn’t start until your design is finalized, so the earlier you lock in finishes, the earlier the clock starts. Cambria quartz slabs get templated after the cabinets are set, then fabricated, adding another 10-14 days from template to install.

Neither of these is a delay. They’re the schedule, and hiding them from homeowners is how contractors create unhappy clients who were promised a six-week finish and got a twelve-week one.

We use premium brand partners across every trade, and that cuts both ways. You get a kitchen built to last, backed in writing, but the trade-off is you can’t swap a custom cabinet order for an in-stock alternative without compromising the design you agreed to. We’d rather tell you that up front than pretend a warehouse-grade cabinet will arrive by Friday.

If you go with premium finishes, expect them to shape the calendar. We’ll give you the real dates before you sign, with the 0% financing for 18 months and $1,000 off projects over $10,000 in place so budgeting isn’t a guess either. Upfront pricing, no surprises.

Timeline by Scope: Cosmetic Refresh vs. Full Gut

The single biggest variable in your timeline is scope, not contractor speed.

  • Cosmetic refresh: new hardware, backsplash, and countertops can run 2-3 weeks. Backsplash installs land at $800-$2,500, and countertop swaps at $2,000-$6,500. No rough-in, no inspection hold, minimal risk.
  • Cabinet-only swap: 3-4 weeks if the layout stays put and no plumbing moves. Cabinet installs run $4,000-$13,000.
  • Full gut-remodel with layout changes: 10-16 weeks minimum in Lewisville once permit and inspection buffers are factored in. This is where rough-in and inspection hold points come into play.
  • Adding an island or moving a sink: tacks on 1-2 weeks for the extra rough-in, inspection cycle, and re-templating. Islands run $3,000-$10,000 on their own.

Layout changes are the quiet culprit. Any time you move a wall, a drain, or a gas line, you’re back into rough-in and inspection territory, and the calendar resets accordingly.

How the 24/7 Live Answer Changes the Experience

Timeline anxiety is real, and it’s the thing that drains a homeowner’s trust faster than a slow phase. When you can call at 9pm on a Thursday and get a real human with a real status update, you make better decisions. You’re not sitting on an assumption that turns into a panic.

Calls to Groundwork Construction Co. of Lewisville are answered by a live person 24/7. No voicemail, no waiting until Monday. Technicians on your job are background-checked and arrive in uniform, so the people in your home are the same people on the schedule. That last piece matters more than it sounds: a lot of remodeling horror stories start with an unmarked van and a crew nobody verified.

FAQs

Getting started with Groundwork in Lewisville

Every project starts with a conversation and a written price. Here is how to take the first step.

A project lead walking the house with the homeowner during a free estimate

Free on-site estimate

A project lead walks the job with you, measures it and hands you a written, line-item price. No obligation.

Book an estimate
A crew arriving at a home with materials and tools

Your Lewisville team

A local vetted partner works across Lewisville and the towns around it, to the same written standard as every Groundwork job.

Areas we serve
A worker laying floor protection before work starts

Read our written promise

What we promise on every job, written down, with the terms spelled out before any work starts.

Our promise
Need Construction help in Lewisville? Licensed & insured · free written estimates
Call (844) 560-4467
Local Service Coverage

Request a Free Estimate in Lewisville

Tell us what you need - Groundwork Construction Co. of Lewisville responds fast. No obligation.

By submitting this form you agree to our Privacy Policy and consent to be contacted by phone, email or SMS about your request, including by local professionals who may handle it.

Prefer to text? Send a Text
Call Now - 24/7 Dispatch