Highland Park’s older homes sit on tight lots with mature trees, which is why a Garage Conversion ADU here rarely starts with the garage. In most Highland Park cases the shell already exists, so the work is interior: new framing, utilities, insulation, finishes, and the permits to make it legal. Our Garage Conversion ADU work in Highland Park, TX runs $45,000 – $130,000 depending on scope, and the typical job takes 10 to 16 weeks. Call (844) 560-4467 to schedule a free on-site estimate.
How we handle a Garage Conversion ADU in Highland Park, step by step
The first thing we tell Highland Park homeowners is that the conversion itself is the easy part. Under the town’s design-review process and its separate building inspection department, the front half of the schedule belongs to the paperwork. Here’s what actually happens, in order.
Days 1 – 3: walkthrough, measurements, and scope decisions
We measure the existing garage down to the studs, check the foundation and roof structure, and identify anything that will trip an inspection later, such as old wiring, single-pane wood windows, or a slab that has settled unevenly on the black clay under Highland Park. By the end of this visit you decide the layout: one room or a studio with a kitchenette, where the bathroom goes, and whether the garage door opening gets framed in or kept as a glazed feature. Nothing is ordered yet.
Weeks 1 – 3: design, engineering, and permits
Drawings go to the town for review. If the garage sits near a protected tree or the change alters the front elevation, expect additional review time before approval. We handle the submittal and any corrections. This is the stage where most projects lose weeks, so we start it before any material is ordered. Highland Park’s separate inspection department means we schedule against its calendar, not Dallas’s.
Weeks 3 – 5: demolition and rough-in
Old garage doors and tracks come out, any existing slab is assessed, and the space gets framed, insulated, and wired for its new use. Plumbing gets roughed in for the bathroom and kitchenette, HVAC is sized and installed, and hot water is added. Rough electrical, plumbing, and mechanical inspections all happen here before walls close.
Weeks 5 – 10: finishes and fixtures
Drywall, paint, flooring, trim, cabinets, and fixtures go in. This is where a garage conversion ADU in Highland Park starts to feel like a finished home rather than a remodeled garage. We coordinate the cabinet and countertop selection around this window so your lead times don’t hold up the schedule.
Weeks 10 – 16: final inspections, punch list, and handoff
Final inspections clear, then we walk the space with you, fix anything on your punch list, and hand over the warranty paperwork. Built to last, backed in writing. If you’re stacking this with other property work, a lot of neighbors pair it with Asphalt Driveways & Resurfacing in Highland Park so the driveway can be reworked after construction traffic.
What you’ll choose between on a Highland Park garage conversion
Most of the decisions on this job come down to a handful of trade-offs. Here’s what actually matters:
- Open studio vs. one-bedroom. An open plan is cheaper and reads larger, but a bedroom needs an egress window, a real door, and a closet. Budget for a few thousand more for the bedroom.
- Kitchenette vs. full kitchen. A two-burner cooktop and compact sink is enough to call it a separate living space. A full kitchen means more electrical, more ventilation, and a higher price. Kitchenette is the value choice here.
- Bathroom rough-in location. Put the bathroom near the existing plumbing stack and you save real money. Move it across the garage slab and you’re breaking concrete, re-sloping drains, and adding a few thousand dollars. Ask us first before you fall in love with a layout.
- Quartz countertops vs. solid surface. Quartz like Caesarstone holds up to daily use and looks right in a Highland Park home. Laminate is much cheaper and shows wear faster. For a rental or a long-term family suite, quartz pays off.
- Fixtures and finishes. We pull from brands like Kohler and Moen for the bathroom, Blanco for a compact sink. A builder-grade faucet is fine for a renter, less so for an Airbnb you’re trying to sell on photos.
- HVAC and insulation. A ducted split system gives you the best comfort. A mini-split is cheaper, quieter, and easier to fit in an older garage attic. We size the system to the finished space, not the original garage.
- Window grade. Single-pane wood windows in the original garage will not pass an inspection that requires egress. Impact-rated glass is worth the cost in North Texas’s hail corridor. Basic double-pane is fine on the non-egress openings.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
What a Garage Conversion ADU costs in Highland Park, TX
Expect $45,000 – $130,000 for a Garage Conversion ADU in Highland Park. Most of our jobs land between $65,000 and $95,000. The low end is a small, single-room studio with a bathroom and kitchenette sharing the existing plumbing wall. The high end is a one-bedroom with a full kitchen, a new HVAC system, and glazed garage-door feature.
The variables that push a job up or down:
- Garage size and ceiling height. A two-car garage is a different job than a single. Higher ceilings cost more to fill but give you better resale on the finished unit.
- Existing condition. Older Highland Park garages often have knob-and-tube wiring, cast-iron drains, or a cracked slab. Any of those adds $3,000 – $12,000.
- Plumbing and electrical location. A bathroom near the existing wet wall is cheap. Moving it across the slab is not.
- Finish grade. Standard builder-grade materials sit at the bottom. Quartz counters, tile bathrooms, and custom cabinetry push to the top.
- Permit scope. A conversion that just changes interior use is a smaller permit. A conversion that adds square footage to the heated envelope gets more review and a longer inspection list.
Every estimate is written line-item, upfront pricing, no surprises. If your project goes above $10,000 (every garage conversion ADU in Highland Park will), you’re set for $1,000 off projects over $10,000 and 0% financing for 18 months. What the estimate covers: labor, permits, materials, dumpster, and final inspections. What it typically doesn’t cover unless you ask: new driveway apron, landscaping repair, or a new roof on the standalone garage if the existing one is failing.
See the difference
Before
After
Before
After
Before
AfterWhat Highland Park homes specifically do to this job
Highland Park is almost fully built out and architecturally controlled, so nearly every garage conversion here is a renovation under review rather than a new build. The town runs its own building inspection department, separate from Dallas, and the design-review and Historical Review Board approvals can stall a project on a protected live oak’s root zone or a variance request before a shovel moves. Because the housing stock dates largely from the 1910s – 1930s, we routinely open a garage and find pier-and-beam framing, early wiring, cast-iron drains, or original single-pane wood windows. The older a garage is, the more we build into the plan for surprises that the first walkthrough alone won’t reveal. And the black clay under Highland Park moves with the wet-dry cycle. That’s why pier replacement and slab correction are part of the conversation before the finishes go in. We cover Highland Park including ZIP 75205.
Serving Highland Park, TX – Our Local Coverage Area
We serve Highland Park and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently asked – Garage Conversion ADU in Highland Park
How long does a Garage Conversion ADU take in Highland Park?
Expect 10 to 16 weeks from permit submittal to final inspection. The construction itself is 6 to 9 weeks. The front end, including town design review and the garage’s own inspection schedule, can take the rest. Call (844) 560-4467 for a realistic timeline based on your garage and lot.
Do I need a permit for a garage conversion in Highland Park?
Yes. Any conversion that turns a garage into a habitable space requires a building permit, and Highland Park runs its own inspection department separate from Dallas. Plans also go through the town’s design-review process. We pull and manage the permits for every job.
Can a garage conversion be done without moving plumbing or structure?
In most cases, yes. A bathroom and kitchenette placed against the existing wet wall and using the current slab and roof structure avoids major structural change. The trade-off is layout flexibility: you get the space the garage already gives you, not a completely redesigned footprint.
What does a Garage Conversion ADU cost in Highland Park?
$45,000 – $130,000, with most jobs landing between $65,000 and $95,000. Size, existing wiring and plumbing, finish grade, and permit scope drive the number. Call (844) 560-4467 for a written line-item estimate, no charge.
What warranty comes with a Garage Conversion ADU?
Every Garage Conversion ADU is covered by our 730-Day Done Right Promise. If it isn’t done right, we make it right. That covers workmanship for two full years, which is one of the longest guarantees in residential construction. Call (844) 560-4467 with questions before you sign anything.
Ready for a real number on your Highland Park garage conversion?

Call (844) 560-4467 to schedule your free on-site estimate. We’ll walk the garage with you, check the foundation and existing wiring, talk through layout options, and hand you a written line-item estimate within a few days. No pressure to sign, no surprises in the fine print. If your plans go beyond the garage, the wider project falls under Home Additions & ADU in Highland Park, and our Home Additions & ADU work often pairs with new hardscape out front, including Concrete Driveways & Concrete Work in Highland Park. Calls are answered by a live person, 24/7.