New Detached ADU in The Colony: What It Costs and How Long It Takes
A new detached ADU in The Colony runs $45,000 – $130,000, and a full build typically takes 4 to 7 months from the first site visit to the final inspection. That range covers a standalone structure on your lot: foundation, framing, roof, utilities run out from the main house, and finish-out. Smaller one-bedroom units land near the low end; a two-bedroom with a full kitchen and its own laundry sits near the top. Call (844) 560-4467 and we’ll walk your lot, check setbacks, and put a real number in front of you instead of a ballpark.
How the Build Actually Runs, Stage by Stage

The sequence for a detached ADU is close to building a small house, because that’s what it is. Here’s the honest timeline and where you make decisions.
Stage 1: Site check and layout (week 1)
We walk the yard and confirm the buildable footprint against setbacks, easements, and where your sewer or septic ties in. You decide the placement: how much yard you’re willing to give up, whether the unit’s entry faces the alley, the street, or a side gate, and how it connects to the main house. This is where most surprise costs get caught early, especially if a utility line runs where you wanted the slab.
Stage 2: Plans, permits, and inspections (weeks 2 – 8)
Drawings get drawn, engineering gets stamped where the soil report requires it, and the packet goes to the city. The Colony reviews ADU plans for setback, height, lot coverage, and utility connections, and the process usually eats four to six weeks depending on plan review volume. You’ll see inspection stops at foundation, framing, rough-in electrical and plumbing, and final. Nothing gets buried in a wall before an inspector signs off.
Stage 3: Site prep and foundation (weeks 8 – 11)
We clear and grade the footprint, form the slab, and set the plumbing under it. North Texas clay moves, so the foundation detail is not where anyone should get creative or cheap. You decide at this stage whether to run a separate water meter, how the unit drains, and where the electrical conduit surfaces.
Stage 4: Framing, roof, and envelope (weeks 11 – 18)
Frame, sheathe, roof, and windows go in. This is the longest single stretch and the one most exposed to weather. Our technicians have up to 12 years of experience reading a site for drainage and storm exposure, and it matters here: a roof that’s flashed badly will show up in your first spring hail season, not your first year, which is why the workmanship is backed by our 730-Day Done Right Promise.
Stage 5: Systems and finish (weeks 18 – 26)
Electrical, plumbing, HVAC, insulation, drywall, flooring, cabinets, and fixtures. You pick finishes here, and those picks are the single biggest lever on the final bill after size. Then final inspection, punch list, and keys. Most of our ADU builds finish inside six months once permits clear.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices You’ll Actually Make, and What Each One Costs You
Detached ADUs aren’t one product. The gaps below separate a $50,000 build from a $125,000 one, and none of them are cosmetic afterthoughts.
- Footprint and bedroom count. A studio or one-bedroom at 500 – 650 sq ft keeps you near the low end. A two-bedroom pushing 900 – 1,000 sq ft moves you toward the high end. More square footage means more slab, more roof, more wire, more everything.
- Roof system. Architectural asphalt shingles are the value pick and hold up to North Texas hail reasonably well. Standing-seam metal costs 2 – 3x as much up front and shrugs off hail; it’s worth it if you plan to keep the unit for 30 years. We install CertainTeed and Owens Corning shingle systems on the majority of our ADU roofs.
- Windows and doors. The Colony sits in hail and high-wind country, and wind-rated windows and impact-rated glazing cost more but reduce storm damage and insurance friction. This is not the line item to cut.
- Utilities: separate or tied in. Running electrical and water from the main house is cheaper but ties the two structures together on one meter. Separate service and a sub-meter cost more and make the unit easier to rent, sell, or hand to family without an awkward shared bill.
- Kitchen and bath finish level. Stock cabinets and a basic vanity keep the budget in line; a full custom kitchen pushes both the cost and the timeline. Pick finishes before framing, not after drywall, or you’ll be paying for changes.
What a New Detached ADU Costs in The Colony, TX

Plan on $45,000 – $130,000 for a new detached ADU in The Colony, with most of our builds landing between $70,000 and $110,000. That’s a wide range because five things move the number, and you control all of them.
- Size. Every additional 100 sq ft adds roughly $12,000 – $20,000 across foundation, framing, roof, and finish.
- Site conditions. A flat, clean lot is cheap. Sloping ground, mature trees to work around, or a long utility trench from the main house adds real cost.
- Utility distance and configuration. The farther the unit sits from the house, the more trenching, conduit, and pipe you pay for. Separate meters add cost but pay off if the unit will ever be rented.
- Finish grade. Builder-grade flooring and stock cabinetry versus custom throughout can swing the interior by $15,000 or more on the same footprint.
- Permit and engineering scope. Soil reports, wind-load engineering, and inspections are legitimate line items. Any estimate that skips them is missing money, not saving it.
Your written estimate breaks out foundation, framing, roofing, MEP rough-in, insulation, finishes, permits, and inspections line by line. Upfront pricing means the number you see is the number you pay, and if something on your site turns out differently than expected, we tell you before we touch it. Projects over $10,000 also qualify for $1,000 off, and 0% financing for 18 months is available if you’d rather spread the cost.
See the difference
Before
After
Before
After
Before
AfterWhat The Colony’s Lots and Weather Do to a Detached ADU Build
The Colony is built out and landlocked on the south shore of Lewisville Lake, which changes everything about building an ADU here. There are almost no open lots left in 75056, so an ADU is a build on a lot that already has a house, a driveway, and 40 years of landscaping on it. Most of the homes we work around date from the 1970s through the 1990s, so the yard often already carries an aging fence, a mature tree canopy, and a utility run you have to design around rather than through. Spring hail and high-wind storms are the local reality, and they shape the envelope: wind-rated doors, impact-rated glass, and roof flashing done right the first time. Expansive clay underfoot means the foundation and drainage plan get more attention than they would on sand. Plan review and inspections run through the city, and if you’re in an HOA subdivision, get the architectural committee’s approval on the unit’s footprint and exterior materials before we order a single board.
For the wider scope, this project is part of a full Home Additions & ADU in The Colony program, and you can review our Home Additions & ADU service for how the trades fit together. We cover the whole of The Colony, and homeowners often pair this with Concrete Driveways & Concrete Work in The Colony for the new unit’s approach and Paver Driveways in The Colony if they want the walkway to match the main house.
Serving The Colony, TX – Our Local Coverage Area
We serve The Colony and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked – New Detached ADU in The Colony

Plan on 4 to 7 months from the initial site visit to move-in. Permitting alone typically runs four to six weeks, and the build itself takes three to five months after that. Call (844) 560-4467 for a timeline built around your specific lot.
Yes. A detached ADU requires building permits and inspections for foundation, framing, electrical, plumbing, and final, and skipping them creates a real problem when you sell. We pull the permits, schedule the inspections, and see them through to a passed final. Call (844) 560-4467 and we’ll walk through the review process for your address.
Usually, yes. You can run a new service from the meter and tie utility lines straight to the unit rather than through the house, which keeps disruption in the main home to near zero. The trade-off is added trenching and meter cost. Call (844) 560-4467 to price both approaches.
Most detached ADUs here land between $45,000 and $130,000, with the typical build around $70,000 – $110,000 depending on size, finishes, and how far the unit sits from the main house. Call (844) 560-4467 for a written line-item quote after a free on-site look.
Every ADU we build is covered by the 730-Day Done Right Promise, which means if the work isn’t right, we make it right for two full years. That covers the roof, the envelope, and the systems we install. Call (844) 560-4467 and we’ll send the warranty terms in writing with your estimate.
Get a Real Number on Your Detached ADU
We’ll come to your lot in The Colony, check setbacks and utility runs, and walk you through a written line-item estimate for your new detached ADU, free of charge. Calls are answered by a live person, 24/7, so you can reach us any time to book a visit. One conversation, one site visit, one honest number. Call (844) 560-4467 to schedule your free estimate.
Written by the team at Groundwork Construction Co.