Garage Conversion ADU in Paloma Creek South: What It Takes and What It Costs
A garage conversion ADU in Paloma Creek South typically runs $45,000 – $130,000 and takes 10 to 16 weeks from the first framing inspection to final walkthrough. You’re turning an existing, covered, slab-on-grade bay into a legal, rentable or family-ready unit: new floor assembly over the slab, framed walls where the door was, a full bathroom, a kitchenette, HVAC, and a separate entrance. Call (844) 560-4467 and we’ll walk your garage and give you a written line-item number.
Here in Paloma Creek South, the work that sinks a garage conversion isn’t the framing. It’s the HOA. On these master-planned lots, the architectural review committee sees your front elevation before the city ever pulls the permit, and the biggest question they ask is: what replaces the garage door? Get that one decision wrong and you’re repainting or refacing on your own dime. That’s why we handle the compliance paperwork as part of the job, not as an afterthought.
How we build a garage conversion ADU, stage by stage

The sequence below is what a real conversion looks like on the ground. It isn’t a sales outline; it’s the order the trades actually move in, and it’s why the job takes weeks, not days.
- Days 1 – 3: Assessment and design lock. We measure the slab, check ceiling height and the existing garage-door header, and look at where the water heater, HVAC air handler, and electrical panel sit. You decide the layout: studio versus one-bedroom, galley kitchenette versus a full kitchen wall, and where the unit’s private entry will be. That decision set is what the drawings and the HOA submittal get built from.
- Week 1 – 2: HOA submittal and permit package. We submit the architectural review application with the door-replacement style, color, and any exterior change spelled out. In parallel, the permit set goes to the city. You sign off on the finish schedule here: flooring, paint, fixtures, appliance package. Getting the door style approved first is the move that keeps the whole project on schedule.
- Week 2 – 4: Demo and rough-in. The overhead door comes out, the opening gets framed and sheathed, and the old slab gets prepped. This is where the plumbing and electrical runs go in: a bathroom rough-in, kitchenette circuits, dedicated HVAC, and often a subpanel. If you can keep the new bath near the existing water heater and the panel, you save real money. If you can’t, this is the stage that gets longer.
- Week 4 – 9: Framing inspections, insulation, drywall, and systems. Rough framing, electrical, plumbing, and mechanical inspections happen in sequence here. Insulation, drywall, and the HVAC trim-out follow. This stretch is mostly invisible progress, and it’s the one homeowners get nervous about. We send photo updates so you can see it.
- Week 9 – 16: Finishes, final inspections, and walkthrough. Flooring, tile, cabinetry, countertops, paint, and fixtures go in. Final building inspection and the certificate of occupancy close it out. At the final walkthrough you get your punch list walked with you and your warranty in writing.
The whole thing lives inside the wider scope of your Home Additions & ADU in Paloma Creek South project picture, but a garage conversion is the tighter, faster version of it because the shell already exists.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The options you’ll actually choose between
Most of the money and most of the decisions sit in five places. Here’s the honest trade-off on each.
- What replaces the garage door. A framed wall with a window and a standard entry door is the most common, most HOA-friendly answer. A full glass-panel or French door looks sharp and lets in light but costs more and draws more scrutiny from the architectural committee. On Paloma Creek South elevations, matching the existing brick and trim color is usually the fastest path to approval.
- Flooring over the slab. Luxury vinyl plank handles the slab movement and moisture swings of North Texas clay better than most anything at its price. Engineered hardwood looks warmer and costs more. Tile is durable and cold underfoot. We usually level the slab first, because a garage slab is poured to drain, not to be flat.
- Kitchenette versus full kitchen. A sink, a two-burner cooktop, and a compact fridge keeps the footprint small and the price down. A full kitchen wall with a range and dishwasher pushes toward the top of the range but makes the unit far more rentable. Caesarstone or Kohler finishes are options here if you want the unit to feel finished, not cobbled together.
- Bathroom configuration. A walk-in shower saves space and reads modern; a tub suits families with kids. Vanity and fixture grade is where the budget flexes hardest, and Moen or Kohler fixtures are the ones we spec most often for longevity.
- HVAC approach. A dedicated mini-split is the cleanest answer for a single garage bay and avoids tying into the main house system. Extending the existing system is possible but only if the load calculation supports it, and it can mean upsizing equipment.
What a garage conversion ADU costs in Paloma Creek South, TX

Plan on $45,000 to $130,000 for a garage conversion ADU in Paloma Creek South. The low end is a straightforward studio with a kitchenette, a mini-split, and the new bath near existing plumbing. The high end is a one-bedroom with a full kitchen, a relocated panel, a new slab pour, and premium finishes throughout.
Here’s what moves the number:
- Size and layout complexity. A single bay is one thing; a two-car with a bedroom and a hallway is another. Every added room adds walls, doors, and inspection steps.
- Distance from existing plumbing and electrical. The single biggest variable. Keeping the new bath near the water heater and the panel saves thousands; moving them across the slab adds it back.
- Slab and structural condition. A cracked or out-of-level slab needs a topping pour. The old garage-door header sometimes needs reinforcement.
- Material grade. Builder-standard versus upgraded cabinetry, counters, and fixtures can swing the total by $15,000 or more.
- Permit and HOA scope. A full certificate-of-occupancy conversion costs more in fees and inspection steps than a lighter-touch finish-out.
A written estimate from us lists each trade line by line, includes a clear scope of what’s covered, and holds to no-hassle upfront pricing: the number you see is the number you pay, unless you change the scope. What it doesn’t include, and we say so upfront: landscaping repair outside the unit, furniture, and appliances you choose to supply yourself.
See the difference
Before
After
Before
After
Before
AfterWhat Paloma Creek South homes specifically do to this job
Paloma Creek South is a build-out master-planned suburb off the US 380 corridor in Denton County, ZIP 75068, and almost everything here is 2000s – 2010s production-builder housing: brick veneer, slab-on-grade, composition-shingle roofs. That build era matters for a conversion. The garage bays are typically generous, the panels and water heaters are usually in the garage already (a gift for a conversion), and the ceilings are tall enough for a proper unit. The catch is the HOA. On these tight master-planned lots, the developer-era architectural review often has more say over your exterior than the city permit does: door style, exterior color, window placement, even the shade of the new siding. We write the submittal to match the elevation, and we’ve learned the committee’s preferences on these plats, so we don’t submit something that gets bounced.
The other local factor is the soil. North Texas clay shrinks and swells with the seasons, and garage slabs on these homes move with it. We check for movement before we pour anything, because a conversion built on a moving slab shows cracks in the finish within a year. If your driveway is part of the plan, homeowners often pair a conversion with Asphalt Driveways & Resurfacing in Paloma Creek South or Concrete Driveways & Concrete Work in Paloma Creek South so the new entry reads intentionally.
If you’re weighing a conversion against building from scratch, our Home Additions & ADU service covers the broader options, and you can see everything we do in Paloma Creek South on the service-area page.
Serving Paloma Creek South, TX – Our Local Coverage Area
We serve Paloma Creek South and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently asked about garage conversion ADU in Paloma Creek South

A garage conversion ADU in Paloma Creek South usually takes 10 to 16 weeks from permit-ready drawings to final inspection. The HOA architectural review adds its own window at the front, often a few weeks, which is why we submit the door style and exterior details before demo starts. Call (844) 560-4467 for a timeline built around your specific garage.
Yes, you’ll need a city building permit and, in most Paloma Creek South communities, HOA architectural review approval before work begins. The conversion changes occupancy, electrical, plumbing, and the exterior elevation, so both layers apply. We prepare the submittal and pull the permit as part of the job, and we don’t start demo until both are in hand.
Yes, in many cases. If the new bathroom sits near the existing water heater and the electrical panel is already in the garage, the plumbing and electrical runs stay short and the price lands closer to $45,000. The trade-off is layout: keeping the bath close can constrain the bedroom placement. We walk the garage and tell you which layouts hold without moving the big systems.
A garage conversion ADU in Paloma Creek South runs $45,000 to $130,000, with the low end for a studio and the high end for a one-bedroom with a full kitchen and upgraded finishes. Call (844) 560-4467 for an exact quote. Estimates are free and itemized line by line.
Every garage conversion ADU we build is covered by our 730-Day Done Right Promise: if it isn’t done right, we make it right. That’s one of the longest workmanship guarantees in residential construction. You get the warranty in writing at the final walkthrough, and our technicians bring up to 12 years of experience to the job.
Get a free estimate on your Paloma Creek South garage conversion ADU
Call (844) 560-4467 to schedule a free on-site estimate. We’ll walk the garage with you, talk through layout and HOA requirements, and follow up with a written line-item quote. Calls are answered by a live person around the clock, so you won’t wait until Monday. Project pricing draws on our $1,000 off projects over $10,000 and 0% financing for 18 months for qualified homeowners.