Cabinets & Countertops in Frisco, TX: What the Job Actually Costs
New cabinets and countertops in Frisco typically run $14,000–$45,000 for a full kitchen, with cabinet installation alone at $4,000–$13,000 and countertop installation at $2,000–$6,500. A straight swap of boxes and slabs takes three to six weeks from order to final caulk; anything that moves a sink, a range line or a wall pushes past that. If you want a real number instead of a ballpark, call (844) 560-4467 and we’ll walk your kitchen with you.
How the Work Actually Runs, Stage by Stage

Most homeowners picture a truck pulling up with boxes and a slab. The truth is a sequence where one trade waits on another, and knowing the order is how you avoid a kitchen sitting half-finished for a month.
Stage 1: Measure and order (week 1)
We template the room with a laser and write down every appliance spec, because a 36-inch range that shows up 3/8-inch wider than the drawing ruins a cabinet run. You decide door style, finish, box construction and slab material here. This is also where lead times get locked: semi-custom cabinets in the 6-to-10-week range are common right now, and natural stone slabs get reserved at the yard.
Stage 2: Demo and rough-in (days 1–3)
Old tops and boxes come out on day one. If we’re relocating the sink, adding a disposal circuit or moving the range, the plumber and electrician open walls on day two and the rough inspection happens before anything closes back up. Days two and three are also when you find out what’s behind the drywall: old water damage, a vent that has to shift, or a floor that needs leveling under the new footprint.
Stage 3: Cabinet set (days 4–7)
Base boxes get shimmed and scribed to the wall, uppers get hung and leveled, and the whole run gets fastened as one unit so the countertop has something flat to sit on. Crown, light rail, fillers and toe kick go on at the end of this stage. Cabinets sit a couple of days before templating.
Stage 4: Countertop template and install (days 8–15)
Solid surface and quartz get templated on site, cut at the shop, and installed about a week later. You pick edge profile and sink cutout before templating, not after. Seams land where the fabricator says they’ll land, and we tell you that location in writing before the cut.
Stage 5: Punch and back to you (days 16–21)
Plumbing reconnects, electrical gets finished, hardware goes on, caulk runs, and we do a walkthrough with you at the counter. Anything that doesn’t sit right gets logged and corrected under our 730-Day Done Right Promise. This whole job is usually one slice of a larger scope, and you can see how it slots into Kitchen Remodeling in Frisco if you’re weighing the full picture.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices That Decide Your Price
Every dollar difference between a $14,000 kitchen and a $45,000 one comes down to a handful of decisions. These are the ones we walk through with homeowners before a line gets drawn.
- Cabinet box construction: Particleboard boxes with stapled joints are the cheap end and hold up fine in a dry climate. Plywood boxes with dovetail drawers and soft-close slides cost more and survive a decade of use without sagging. For a busy Frisco household, we usually steer toward plywood.
- Door style and finish: Painted MDF shaker is the affordable workhorse. Solid wood and thermofoil both have their place, but thermofoil peels in high-heat spots near the range. Full-overlay doors cost a bit more and clean up easier than partial.
- Countertop material: Laminate is the budget pick and short-lived near a sink. Quartz is the default now: non-porous, no sealing, and it holds up to the granite-pattern taste most of our Frisco clients want. Natural stone (granite, marble, soapstone) runs higher and needs sealing. Cambria and KraftMaid are the two brands we pull most often for kitchens.
- Slab vs. modular: A single slab with a waterfall edge on an island costs more than three separate pieces with seams. Larger slabs mean fewer seams and cleaner sightlines, but they’re heavier to move and pricier per square foot.
- Edge and sink: A standard eased edge is cheap. A mitered or beveled edge adds cost and craftsmanship. An undermount sink is worth the upcharge over a drop-in; the seal line matters more than the bowl material.
Flooring, backsplash and appliance swaps have their own pages if you want to go deeper, but they’re separate line items here.
What Cabinets & Countertops Costs in Frisco, TX

Frisco kitchens land in the $14,000–$45,000 range for cabinets and countertops together, and the number moves with five things: room size, cabinet grade, slab material, whether plumbing or electrical has to move, and how much of the old kitchen gets torn back to studs. Here’s the honest line-item view.
| Line item | Typical Frisco range |
|---|---|
| Cabinet installation | $4,000–$13,000 |
| Countertop installation | $2,000–$6,500 |
| Backsplash installation | $800–$2,500 |
| Kitchen island installation | $3,000–$10,000 |
| Small kitchen scope | $9,000–$20,000 |
| Full kitchen scope | $14,000–$45,000 |
A written estimate from us includes demo, cabinet supply and install, slab fabrication and install, plumbing and electrical reconnects within the cabinet area, and cleanup. It usually does not include appliance purchase, structural changes (moving a wall or window), flooring, or drywall patching beyond the cabinet run itself. Ask for the scope in writing, and hold any contractor to it. The number you see is the number you pay, and there are no change orders hiding in the last week.
See the difference
Before
After
Before
After
Before
AfterWhat Frisco Homes Specifically Do to This Job
Almost every kitchen we open in Frisco was built after 1990, in a master-planned subdivision, on a slab. That changes this job in ways a homeowner moving from an older city won’t expect. Because the city grew so fast, entire streets of 1990s homes hit their first major remodel in the same stretch of years. We routinely open a kitchen in 75035 and find that the neighbor three doors down is doing theirs the same month, because the cabinets and laminate counters were all installed by the same builder in the same year and have all failed the same way.
The clay soil underneath Frisco moves with every wet-dry cycle, and that shows up as foundation movement rather than cabinet failure. If the floor is out of level by more than about 3/8 inch across the run, the cabinets will fight us, and the counters will telegraph the slope in a way you’ll notice every morning. We check for that first. HOA rules in the master-planned communities here also matter for anything that touches the exterior wall or a visible finish, so if an island vent or a range hood is moving, read your architectural guidelines before demo day. And because North Texas hail and high wind drive near-annual roof and exterior repairs, we often find water intrusion traces around window heads once the uppers come down. Frisco has its own permitting process through the city’s development services office, and cabinet and countertop swaps typically don’t require a structural permit, but any layout change that moves a wall, a gas line or the plumbing rough-in does. We pull what’s needed and make sure the inspection passes.
Serving Frisco, TX – Our Local Coverage Area
We serve Frisco and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked - Cabinets & Countertops in Frisco

About three to six weeks from order to final walkthrough, with the physical work itself concentrated in roughly three weeks. Custom-order cabinets add lead time, and slab templating typically adds a week between demo and install. Call (844) 560-4467 for a schedule based on the exact cabinets and stone you’re considering.
Usually not for a like-for-like swap, but you do for anything that moves a wall, a gas line, or the plumbing rough-in. The city’s development services office handles those permits, and our technicians will tell you upfront which parts of your job fall into that category.
Yes, and most of our Frisco jobs do exactly that. Keeping the sink and range in place trims the cost and the timeline; a same-location swap is often a two-week build. Moving them is what pushes the price up and the schedule out.
$14,000–$45,000 for a full kitchen, or $9,000–$20,000 for a smaller scope. Cabinet installation alone is $4,000–$13,000, countertop installation is $2,000–$6,500, and a backsplash runs $800–$2,500. For an exact written quote, call (844) 560-4467. Estimates are free.
Our 730-Day Done Right Promise covers the labor and installation for two full years. Manufacturer warranties on KraftMaid cabinets or Cambria quartz run longer and pass to you. Both are put in writing before we start, and both apply to Frisco jobs the same way they do anywhere else.
If you’re also converting a garage into a living space or adding a workshop on the same property, homeowners often pair this with a Garage Conversion ADU in Frisco while the cabinets are on order, or a New Detached ADU in Frisco for a bigger footprint. Those are separate projects but share the same trades, and we can time them together if the schedule allows. Our Kitchen Remodeling service hub has the wider view if you want to think about the whole room. We cover all of Frisco, including the ZIPs 75034, 75035 and 75033.
Get a Free Estimate on Cabinets & Countertops in Frisco, TX
Call (844) 560-4467 and a live person picks up, day or night. We schedule a free on-site estimate for your Frisco kitchen, template the space, and hand you a written line-item quote so you know exactly what’s included before you sign anything. If you’re weighing timing, we’ll be straight with you about lead times. Financing at 0% for 18 months and $1,000 off projects over $10,000 are available. Free estimate and design consult, no obligation.